Welcome
Thank you for visiting our website where you can read about our development of new homes north of Amersham Road in Hazlemere, find answers to commonly asked questions, as well as log any issues or questions on our interactive map.
Buckinghamshire Council granted planning permission in October 2023 for this development on part of the HW8 site allocated in Wycombe District’s Local Plan 2019. Construction started in December 2024 and this website will enable you to keep up to date with how works progress.
The planning application 21/08364/FUL can be viewed on Buckinghamshire Council’s planning portal.
Concurrently, a detailed Reserved Matters application for the northern section of the site is being prepared by Hawridge Land, which will be submitted to Buckinghamshire Council for determination later this year.
We will be continuing to publish the latest news on our website here as the programme commences.


Report an issue
Please use our interactive map to report any issues on site. You can drop a pin on a specific location and provide a description. One of our team will respond as soon as possible.
HW8 at a glance

259 new homes, including affordable housing, helping to meet identified local need for new housing in the area.

Retained and enhanced woodland and open green space, with improved landscape buffer zones on the edge of the site.

Allocated for new housing in the Wycombe District Local Plan, adopted in 2019.

Achieving at least 10% biodiversity net gain.

Delivering vital financial contributions to local infrastructure through CIL and Section 106.

Centrally located new sports and play areas.

Comprehensive layout and masterplan, underpinned by a collaborative approach.

Improved pedestrian and vehicular access, updated to reflect local feedback.
Working with the local community
Bellway Homes has set up a Liaison group with local representatives. The group’s purpose is to discuss the site, next steps and to ensure regular and proactive updates are provided.
Minutes of the Liaison group’s meetings are being uploaded on this website in the News section.

Timeline
October 2023
- Bellway’s detailed application granted planning consent by Buckinghamshire Council
Spring 2024
- Section 106 agreements signed
December 2024
- Start on site
February 2025
- Roads base Tarmac in phase 1a and piling start on site
March 2025
- Brick work start
Winter 2026
- First residents move in
Site updates
Visit our news page to find out the latest updates in relation to the site.

FAQs
What was the cause of a fire on the site?
On 25 April 2024 Bellway Homes attended site after the Fire service alerted the company to a fire having been started on site. It was discovered that a break-in had happened, illegally tipped waste dumped and then set alight. After the Fire service put out the fire, the Environment Agency asked for testing to be carried out on the waste, before being cleared from the site.
What was the cause and consequences of the flooding?
On the night of 4 January 2025 there was snowfall, followed by extremely heavy rain and on 5 January water ran down through woodland behind Badger Way causing flooding. Due to concerns about the potential impact on the local badger population, ecologists conducted a survey. This found that the badgers were unharmed.